Step 1 - Remove & discard tape holding funnel arm in place. (Figure 1)
Step 2 - Remove & discard two silicon tubes between funnel guide &
housing. (Figure 2)
Step 3 - Remove four screws in front housing panel. (Figure 3)
Step 4 - Remove & discard shim under transducer. (Figure 4)
Step 5 - Replace housing panel and secure four screws. (Figure 3)